11704930648Forthwind Offshore Development Phase 1 - Section 36 Variation - Decision NoticeCreated by RebeccaB.100017718data_sourceund155921810115592239780015592239780- <p>Varied section 36 consent issued in respect of the Forthwind Offshore Wind Demonstration Project.</p>
<p>The variation application sought to amend the s.36 consent granted on 21 December 2016 to allow the maximum installed consented capacity to increase from 18 Megawatts ("MW") to a maximum of 29.9MW.</p>
filtered_html<p>Varied section 36 consent issued in respect of the Forthwind Offshore Wind Demonstration Project.</p>
<p>The variation application sought to amend the s.36 consent granted on 21 December 2016 to allow the maximum installed consented capacity to increase from 18 Megawatts ("MW") to a maximum of 29.9MW.</p>
- 1871
- 9117330648Decision Noticepublic://decision_notice_redacted.pdfapplication/pdf87354711559218057document<_drafty_revision_requested>FIELD_LOAD_CURRENT11
- 1866
- 1843
- 1911
- 2019-05-30 00:00:00Europe/LondonEurope/Londondatetime
- sioc:Item
- foaf:Document
- dc:title
property- dc:date
- dc:created
xsd:dateTimedate_iso8601- dc:modified
xsd:dateTimedate_iso8601- content:encoded
property- sioc:has_creator
rel- foaf:name
- sioc:num_replies
xsd:integer- sioc:last_activity_date
xsd:dateTimedate_iso8601https://marine.gov.scot/data/forthwind-offshore-development-phase-1-section-36-variation-decision-noticeRebeccaBa:5:{s:16:"ckeditor_default";s:1:"t";s:20:"ckeditor_show_toggle";s:1:"t";s:14:"ckeditor_width";s:4:"100%";s:13:"ckeditor_lang";s:2:"en";s:18:"ckeditor_auto_lang";s:1:"t";}10819411704917718needs_reviewpublished23672155922397811Forthwind Offshore Development Phase 1 - Section 36 Variation - Decision Notice155922397810819411704917718needs_reviewpublished23672155922397811Forthwind Offshore Development Phase 1 - Section 36 Variation - Decision Notice155922397810819411704917718needs_reviewpublished23672155922397811Forthwind Offshore Development Phase 1 - Section 36 Variation - Decision Notice1559223978